Speaking in the House of Lords on 22 October 2025
Debate
Planning and Infrastructure BillContribution
67: After Clause 51, insert the following new Clause—
“Planning permission etc: extension of time in event of legal challenge(1) The Town and Country Planning Act 1990 is amended as set out in subsections (2) and (3).(2) In section 91 (general condition limiting duration of planning permission), for subsections (3A) and (3B) substitute—“(3A) In subsections (3B) to (3BB)—“implementation period” means the period before the end of which a development to which a planning permission relates must be begun (see subsections (1) and (3));“relevant proceedings” means proceedings to challenge the validity, in respect of the development of land in England, of a grant of planning permission or of a deemed grant of planning permission.(3B) If a person is given permission by a court to bring relevant proceedings, the implementation period is extended by one year.(3BA) If a party to relevant proceedings is given permission to appeal to the Court of Appeal against a decision determining the challenge, the implementation period is extended by one year.(3BB) If a party to relevant proceedings is given permission to appeal to the Supreme Court against a decision determining the challenge, the implementation period is extended by two years.(3BC) Any extension of a period under subsection (3B), (3BA) or (3BB) is to run concurrently with any other extension of the period under the same subsection (so far as they overlap).(3BD) Any extension of a period under subsection (3BA) is to run consecutively to the previous extension of the period under subsection (3B) (if they would otherwise overlap).(3BE) Any extension of a period under subsection (3BB) is to run consecutively to the previous extension of the period under subsection (3B) and any previous extension of the period under subsection (3BA) (if they would otherwise overlap).(3BF) The references in subsections (3BA) and (3BB) to determining a challenge are to determining it after a full hearing (and accordingly do not include a refusal of permission or leave).”(3) After section 92 insert—“92A Extension of outline planning permission etc in event of legal challenge(1) This section applies where a person is given permission by a court to bring proceedings challenging the validity, in respect of the development of land in England, of—(a) a grant (or deemed grant) of outline planning permission, or(b) the approval of reserved matters under such a permission. (2) Any reserved matters application period or implementation period that is running when the court gives permission to bring the proceedings is extended by one year.(3) If a party to the proceedings is given permission to appeal to the Court of Appeal against a decision determining the challenge, any reserved matters application period or implementation period that is running at that time is extended by one year.(4) If a party to the proceedings is given permission to appeal to the Supreme Court against a decision determining the challenge, any reserved matters application period or implementation period that is running at that time is extended by two years.(5) Any extension of a period under subsection (2), (3) or (4) is to run concurrently with any other extension of the period under the same subsection (so far as they overlap).(6) Any extension of a period under subsection (3) is to run consecutively to the previous extension of the period under subsection (2) (if they would otherwise overlap).(7) Any extension of a period under subsection (4) is to run consecutively to the previous extension of the period under subsection (2) and any previous extension of the period under subsection (3) (if they would otherwise overlap).(8) For the purposes of subsections (2) to (4), an implementation period that is determined by reference to an approval of a reserved matter starts to run when the reserved matters application is made (and the reserved matters application period ceases to run at that point).(9) Subsection (10) applies if a reserved matters application is made without taking advantage of an extension under this section.(10) Any implementation period determined by reference to the approval sought by the reserved matters application is extended by the number of days by which the reserved matter application period is extended under this section.(11) Subsection (12) applies if a reserved matters application period is extended (or further extended) under this section and the reserved matter application is made taking advantage of the extension but before the end of the period as extended.(12) Any implementation period determined by reference to the approval sought by the reserved matters application is extended by the number of whole days remaining in the reserved matters application period (as extended) when the reserved matters application is made.(13) In this section—“implementation period” , in relation to a grant of outline planning permission, means the period before the end of which development to which the permission relates must be begun (see section 92(2)(b), (4) and (5));“outline planning permission” has the same meaning as in section 92;“reserved matters application” means an application for the approval of a reserved matter in pursuance of section 92;“reserved matters application period” , in relation to a grant of outline planning permission, means the period before the end of which a reserved matters application relating to the permission is required to be made (see section 92(2)(a), (4) and (5)).(14) In this section, references to determining a challenge are to determining it after a full hearing (and accordingly do not include a refusal of permission or leave).” (4) In the Planning (Listed Buildings and Conservation Areas) Act 1990, in section 18 (limit of duration of listed buildings consent), for subsections (2A) and (2B) substitute—“(2A) In subsections (2A) to (2BB)—“implementation period” means the period before the end of which works to which a listed building consent relates are required to be begun in pursuance of subsection (1) or (2);“relevant proceedings” means proceedings to challenge the validity of a grant of listed building consent or of a deemed grant of listed building consent.(2B) If a person is given permission by a court to bring relevant proceedings, the implementation period is extended by one year.(2BA) If a party to relevant proceedings is given permission to appeal to the Court of Appeal against a decision determining the challenge, the implementation period is extended by one year.(2BB) If a party to relevant proceedings is given permission to appeal to the Supreme Court against a decision determining the challenge, the implementation period is extended by two years.(2BC) Any extension of a period under subsection (2B), (2BA) or (2BB) is to run concurrently with any other extension of the period under the same subsection (so far as they overlap).(2BD) Any extension of a period under subsection (2BA) is to run consecutively to the previous extension of the period under subsection (2B) (if they would otherwise overlap).(2BE) Any extension of a period under subsection (2BB) is to run consecutively to the previous extension of the period under subsection (2B) and any previous extension of the period under subsection (2BA) (if they would otherwise overlap).(2BF) The references in subsections (2BA) and (2BB) to determining a challenge are to determining it after a full hearing (and accordingly do not include a refusal of permission or leave).”(5) The amendments made by subsections (2) and (4) do not operate to extend any implementation period that has already expired.(6) In relation to proceedings begun before the day on which subsection (2) comes into force (“the commencement date”)—(a) any extension of time under section 91(3B) of the Town and Country Planning Act 1990 that had already arisen before the commencement date as a result of those proceedings is unaffected;(b) subsections (3B) to (3BB) of section 91 of that Act (as inserted by subsection (2)) apply so far as any event in the proceedings giving rise to an extension of time under those subsections occurs on or after the commencement date, but not otherwise.(7) In relation to proceedings begun before the day on which subsection (3) comes into force, section 92A of the Town and Country Planning Act 1990 (inserted by subsection (3)) applies so far as any event in the proceedings giving rise to an extension of time under that section occurs on or after that day, but not otherwise.(8) In relation to proceedings begun before the day on which subsection (4) comes into force (“the commencement date”)—(a) any extension of time under section 18(2B) of the Planning (Listed Buildings and Conservation Areas) Act 1990 that had already arisen before the commencement date as a result of those proceedings is unaffected; (b) subsections (2B) to (2BB) of section 18 of that Act (as inserted by subsection (4)) apply so far as any event in the proceedings giving rise to an extension of time under those subsections occurs on or after the commencement date, but not otherwise.”Member’s explanatory statement
This amendment would extend the time for implementing a planning permission or listed building consent where the permission or consent is challenged in legal proceedings. There would be an extension of one year in all cases, with a further year where the case goes to the Court of Appeal and a further two years where the case goes to the Supreme Court.
About Hansard
Hansard is the official verbatim record of proceedings in the UK Parliament. Every word spoken in the Commons and Lords is recorded and published — this page is a single contribution from that record.
Partner sites