Adrian Ramsay

Adrian Ramsay

Green Party — Waveney Valley

Speaking in the House of Commons on 26 November 2024

Debate

Electricity Grid Upgrades

Contribution

I welcome the chance to discuss matters like this in Westminster Hall—where, in my experience, there is an opportunity to look at the issues and options calmly and without party political point scoring. We must deliver the energy transition at speed, and with community inclusion. The upgrades to the electricity grid are vital for net zero, but how this is done will shape public trust. We can, and must, achieve rapid progress and meaningful community engagement. My constituents in Waveney Valley—like much of East Anglia—face floods, droughts, and farmland at risk of submersion: they understand the urgency, and voted for action in the election. The grid upgrade is essential to connect renewable energy capacity and end reliance on fossil fuels. Indeed, I have spent the last 10 years leading national environmental charities advocating for and advancing renewable energy, speeding up the transition, and advocating for strengthening the grid. The question is how we can best do that. There are significant concerns over this proposed pylon route, as we have heard—concerns about the impact on sensitive nature and heritage sites, including the rural landscape, about the impact on farming, and about the implications for local traffic. This is not just about convenience. We need to make decisions that are right for the long term and resilient to the future climate changes that we face. I want to zoom out, as other speakers have done, and talk about the overall climate emergency and climate breakdown that we are grappling with and working to address. We have seen in Parliament over recent decades a broad consensus on the need for action to be taken: the Climate Change Act 2008 was passed with cross-party support, and the 2050 net zero target was embedded by a later Government, with broad support across the House. We have not had the kind of polarisation that we have seen in the US, and we need to maintain that strong support and to avoid the issue being weaponised so that it becomes divisive and is used for political point scoring, but we risk that happening if we do not take people with us and if people are not heard. The energy transition must be done with communities, not to them—communities need to feel engaged and heard to maintain their support. People want to see action taken. Speed and proper community consultation can go hand in hand; indeed, they must. The best way to accelerate the energy transition is for communities to feel consulted and involved from the outset. If people believe projects are imposed on them without proper engagement, there is a risk of slowing progress and undermining trust in the renewable energy revolution—a revolution that must happen. That is why I want to see us use the time that we have right now. The National Grid consultation closed in July and we face a long delay until a planning application is expected at some point next year—we are not sure when. During this time, other options can be properly considered, and that is all I am calling for: a proper consideration of all the options. National Grid has acknowledged that undergrounding is possible—it is doing it in two small sections of the route—but there remain significant concerns.

More from Adrian Ramsay

Other recent Hansard contributions by the same speaker.

About Hansard

Hansard is the official verbatim record of proceedings in the UK Parliament. Every word spoken in the Commons and Lords is recorded and published — this page is a single contribution from that record.

For Adrian Ramsay's full parliamentary record including voting history, expenses and all other contributions, see the Adrian Ramsay report card.