Oral QuestionRestoration and Renewal Client Board

To ask the hon. Member for Blaenau Gwent and Rhymney, representing the Restoration and Renewal Client Board, what its planned timetable is for starting major works on the Palace of Westminster.

Tabled: 12 February 2026Answered: 26 February 2026

Asked by

Dame Meg Hillier

Labour (Co-op)Hackney South and Shoreditch

Answering Minister

the hon. Member for Blaenau Gwent and Rhymney, representing the Restoration and Renewal Client Board

Answer from Hansard

Nick Smith (Blaenau Gwent and Rhymney)

The Client Board’s recent report recommends a way forward for restoration and renewal. It contains phase 1 works, including seven years’ foundational works for the full programme. These preparatory works can begin once we have approval from both Houses. A final decision on the preferred delivery option is required from both Houses no later than 2030. The main R&R works could begin in 2032.