Written Question·Department for Transport·UIN 19016
A1: Gateshead
Tabled: 10 December 2024
Answered: 16 December 2024
Question
Jerome Mayhew
Conservative — Broadland and Fakenham
To ask the Secretary of State for Transport, what estimate her Department has made of the completion date of the A1 Birtley to Coal House RP2 project.
Answer
Lilian GreenwoodThe schemes in question are in different stages as follows: Four schemes have been completed and are open to traffic.Scheme NameCompletion DateM621 Junction 1-7 EnhancementsCompleted September 2024A585 Windy Harbour to SkippoolCompleted March 2024A19 Down...
ⓘ