Danny Kruger

Reform UKEast Wiltshire

To ask the Secretary of State for Defence, what progress his Department has made on the Ajax armoured fighting vehicle programme trials.

Answer

Luke Pollard
The Armoured Fighting Vehicle AJAX Programme trials continue to progress and remain ongoing. Reliability Growth Trials (RGT) are ongoing and on schedule to complete by December 2026.Regarding the Armoured Vehicle Programme (AJAX) Initial Operating Capabil...