Written Question·Ministry of Defence·UIN 5402
Ajax Vehicles: Procurement
Tabled: 11 September 2024
Answered: 11 October 2024
Question
Danny Kruger
Reform UK — East Wiltshire
To ask the Secretary of State for Defence, when he expects that the initial operating capacity of Ajax armoured fighting vehicles will be delivered.
Answer
Luke PollardThe Armoured Fighting Vehicle AJAX Programme trials continue to progress and remain ongoing. Reliability Growth Trials (RGT) are ongoing and on schedule to complete by December 2026.Regarding the Armoured Vehicle Programme (AJAX) Initial Operating Capabil...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 5402) →