Written Question·Ministry of Defence·UIN 101527
Armoured Fighting Vehicles: Procurement
Tabled: 18 December 2025
Answered: 13 January 2026
Question
Ben Obese-Jecty
Conservative — Huntingdon
To ask the Secretary of State for Defence, pursuant to the answer of 16 December 2025 to question 98882 on Armoured Fighting Vehicles: Procurement, what the £3,777,000 in constructive losses related to Project Rarden in the 2024-25 Ministry of Defence Acc
Answer
Luke PollardI refer the hon. Member to the answer to his Question 98882 which remains extant. There has been no money spent or specific work carried out under Project Rarden in the last ten years, there is no further data prior to this date. Project Rarden is a legac...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 101527) →