Written Question·Ministry of Defence·UIN 105259
Artillery: Procurement
Tabled: 13 January 2026
Answered: 21 January 2026
Question
James Cartlidge
Conservative — South Suffolk
To ask the Secretary of State for Defence, with reference to his Department's press release entitled UK and Germany sign £52m contract for cutting-edge artillery, published on 28 December, when he expects RCH 155 to conclude its assessment phase.
Answer
Luke PollardThe joint Assessment Phase, in collaboration with Germany, is expected to conclude in Quarter four of 2029. Similarly to Germany, the Department's aim is to commit to production on the common build standard as soon as possible, subject to receiving a cost...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 105259) →