Written Question·Ministry of Defence·UIN 106626

Artillery: Procurement

Tabled: 19 January 2026
Answered: 27 January 2026

Question

Will Stone

LabourSwindon North

To ask the Secretary of State for Defence, with reference his Department’s press release on 28 December 2025 regarding the signing of a £52 million contract for RCH 155, how much UK content will be part of the production of the capability.

Answer

Luke Pollard
The Early Capability Demonstrator platforms of the RCH155, two for Germany and one for the UK, will be built in Germany for joint testing.The project remains in its assessment phase and a production contract has not yet been placed.