Written Question·Department for Energy Security and Net Zero·UIN 115573

Batteries and Data Centres

Tabled: 24 February 2026
Answered: 9 March 2026
Named Day

Question

Ms Polly Billington

LabourEast Thanet

To ask the Secretary of State for Energy Security and Net Zero, what assessment his Department made of the potential merits of delaying connection offers for some protected battery projects and data centres to allow NESO and DESNZ to undertake other key a

Answer

Michael Shanks
NESO’s connections reforms have reduced the queue for generation and storage connections by over half, with the queue now largely in line with the capacity ranges set out in the Clean Power 2030 Action Plan. We are aware that the volume of batteries in th...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 115573) →