Written Question·Ministry of Defence·UIN 51111

Boeing E-7

Tabled: 9 May 2025
Answered: 14 May 2025
Named Day

Question

Mr Mark Francois

ConservativeRayleigh and Wickford

To ask the Secretary of State for Defence, pursuant to the Answer of 7 May 2025 to Question 49322 on Boeing E-7, what further test flights are planned for the first E-7 Wedgetail aircraft before it enters its test and evaluation phase.

Answer

Maria Eagle
The Wedgetail programme has already entered the flight test programme and has completed three flights. There is a comprehensive ground and flight test programme in 2025 prior to the aircraft being handed over to the Royal Air Force, the exact number of wh...