To ask the Secretary of State for Defence, if he will set out what (a) technical and (b) management issues are causing the delay in the RAF’s E-7 Wedgetail aircraft WT001 flight test programme; and what steps his Department is taking to ensure the late-20
Answer
Maria EagleThe Wedgetail programme has already completed three test flights and will continue to undertake comprehensive ground and flight tests throughout 2025 to achieve the approved In-Service Date. Engagement continues with Boeing and the Ministry of Defence to ...
ⓘ