Question

Mr Mark Francois

ConservativeRayleigh and Wickford

To ask the Secretary of State for Defence, when the Boxer armoured vehicle programme is expected to achieve Initial Operating Capability.

Answer

Luke Pollard
The approved Initial Operating Capability of the Mechanised Infantry (Boxer) programme is currently Q4 2025. It is under review and an update will be provided shortly. The programme has faced some delays that have primarily resulted from global supply cha...