Written Question·Ministry of Housing, Communities and Local Government·UIN 29450

Building Safety Regulator

Tabled: 6 February 2025
Answered: 14 February 2025
Named Day

Question

Neil Coyle

LabourBermondsey and Old Southwark

To ask the Secretary of State for Housing, Communities and Local Government, whether she plans to issue new guidance to help reduce Building Safety Regulator workload.

Answer

Alex Norris
We are aware that there have been delays for applicants using the building regulation approval process for Higher Risk Buildings. The Building Safety Regulator (BSR) has told applicants to currently plan on the basis of 20 weeks to clear gateway two, alth...