Written Question·Ministry of Housing, Communities and Local Government·UIN 82548
Building Safety Regulator
Tabled: 15 October 2025
Answered: 22 October 2025
Question
Darren Paffey
Labour — Southampton Itchen
To ask the Secretary of State for Housing, Communities and Local Government, when the new Fast Track Process for Building Safety Regulator applications will be live; and what the criteria for it will be.
Answer
Samantha DixonThe Innovation Unit (previously referred to as the Fast Track process) was launched on the 4th August with the majority of cases on track to meet the 13-week target. The Innovation Unit has initially been used only for new-build applications. As its capac...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 82548) →