Question

Neil Coyle

LabourBermondsey and Old Southwark

To ask the Secretary of State for Housing, Communities and Local Government, how many applications have waited longer than the 12-week timeframe that the Building Safety Regulator says it will take to complete its process in the last 12 months.

Answer

Samantha Dixon
The Building Safety Regulator (BSR) has reported that 930 Gateway 2 applications decided in the last 12 months (between 24 October 2024 and 23 October 2025) took longer than 12 weeks to reach a decision.The BSR is already making operational and policy cha...