Charlie Dewhirst
Conservative — Bridlington and The Wolds
To ask the Minister for the Cabinet Office, with reference to the National Infrastructure and Service Transformation Authority's Annual Report 2024–25, published on 11 August 2025, for what reason no evaluation was completed for the Rosa renewal project.
Answer
Ms Abena Oppong-AsareThe Rosa Renewal Project was subject to the appropriate National Infrastructure Service Transformation Authority oversight, with the project coming to a formal close in March 2025. The project achieved a GREEN Delivery Confidence Assessment as part of its...
ⓘ