Written Question·Cabinet Office·UIN 73306

Cabinet Office: ICT

Tabled: 29 August 2025
Answered: 3 September 2025

Question

Charlie Dewhirst

Conservative — Bridlington and The Wolds

To ask the Minister for the Cabinet Office, with reference to the National Infrastructure and Service Transformation Authority's Annual Report 2024–25, published on 11 August 2025, for what reason no evaluation was completed for the Rosa renewal project.

Answer

Ms Abena Oppong-Asare
The Rosa Renewal Project was subject to the appropriate National Infrastructure Service Transformation Authority oversight, with the project coming to a formal close in March 2025. The project achieved a GREEN Delivery Confidence Assessment as part of its...
ⓘ

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 73306) →