Written Question·Department for Transport·UIN 54014

Cambridge South Station: Construction

Tabled: 21 May 2025
Answered: 3 June 2025

Question

Mr Richard Holden

Conservative — Basildon and Billericay

To ask the Secretary of State for Transport, pursuant to the Answer of 20 May 2025 to Question 51962 on Abellio Greater Anglia and c2c: Standards, what her planned timeline is for the improvements to Cambridge South Station; when the Transport and Works A

Answer

Simon Lightwood
The Transport and Works Act Order for Cambridge South was granted in December 2022, and construction work began on site in February 2023. We expect the new station to open early in 2026; an exact date will be confirmed later in the year.