Written Question·Department for Energy Security and Net Zero·UIN 53450

Carbon Capture and Storage: Merseyside and Tees Valley

Tabled: 19 May 2025
Answered: 28 May 2025

Question

James McMurdock

Independent — South Basildon and East Thurrock

To ask the Secretary of State for Energy Security and Net Zero, what his planned timeline is for the carbon capture sites in Merseyside and Teesside.

Answer

Sarah Jones
Having reached financial close with East Coast Cluster in December 2024, and with the HyNet Transport and Storage Company, operated by Liverpool Bay CCS, in April 2025, construction is already underway, and we expect the Transport & Storage Companies ...
ⓘ

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 53450) →