Written Question·Department for Energy Security and Net Zero·UIN 53450
Carbon Capture and Storage: Merseyside and Tees Valley
Tabled: 19 May 2025
Answered: 28 May 2025
Question
James McMurdock
Independent — South Basildon and East Thurrock
To ask the Secretary of State for Energy Security and Net Zero, what his planned timeline is for the carbon capture sites in Merseyside and Teesside.
Answer
Sarah JonesHaving reached financial close with East Coast Cluster in December 2024, and with the HyNet Transport and Storage Company, operated by Liverpool Bay CCS, in April 2025, construction is already underway, and we expect the Transport & Storage Companies ...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 53450) →