Written Question·Ministry of Defence·UIN 19253

Challenger Tanks: Procurement

Tabled: 11 December 2024
Answered: 16 December 2024
Named Day

Question

Mr Mark Francois

ConservativeRayleigh and Wickford

To ask the Secretary of State for Defence, what the cost of the Challenger 3 main battle tank development programme is including budget increases due to delays.

Answer

Maria Eagle
Through the Armour Main Battle Tank programme, expenditure for Challenger 3 Main Battle Tank delivery as of 13 December 2024 is c£421.167 million.