Written Question·Ministry of Defence·UIN 5886
Clyde Naval Base
Tabled: 4 October 2024
Answered: 15 October 2024
Named DayQuestion
Mr Mark Francois
Conservative — Rayleigh and Wickford
To ask the Secretary of State for Defence, when the repair to the submarine lift at HMNB Clyde is due for completion; and what the estimated cost was of that repair.
Answer
Luke PollardThe shiplift at HMNB Clyde is undergoing scheduled routine maintenance and upgrade work.Costs for key assets in the naval base are included in the routine maintenance contract with Babcock. It would not be appropriate to provide detailed availability of c...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 5886) →