Written Question·Department for Environment, Food and Rural Affairs·UIN 112920

Coastal Erosion and Flood Control

Tabled: 11 February 2026
Answered: 24 February 2026

Question

Gideon Amos

Liberal Democrat — Taunton and Wellington

To ask the Secretary of State for Environment, Food and Rural Affairs, how many completed flood and coastal erosion risk management capital schemes have undergone formal post-project appraisal in each of the last five financial years; and what proportion

Answer

Emma Hardy
Every individual project is managed following the Gateway process set out in the Government Functional Standard for Project Delivery. As a project nears completion, Project Managers are required to test the readiness for service (Gateway 4) and then check...
ⓘ