Written Question·Department for Transport·UIN 24054
Colne-Skipton Railway Line
Tabled: 14 January 2025
Answered: 17 January 2025
Named DayQuestion
Jonathan Hinder
Labour — Pendle and Clitheroe
To ask the Secretary of State for Transport, with reference to the Answer of 6 January 2020 to Question 492 on Colne-Skipton Railway Line, whether her Department has completed the further feasibility work.
Answer
Simon LightwoodAll feasibility work relating to the proposed reinstatement of the Skipton-Colne line has been completed. While there is a strong strategic case for improving connectivity between East Lancashire and the Leeds city region, the scheme is currently unafford...
ⓘ