Written Question·Ministry of Defence·UIN 5885

Devonport Dockyard

Tabled: 4 October 2024
Answered: 15 October 2024
Named Day

Question

Mr Mark Francois

ConservativeRayleigh and Wickford

To ask the Secretary of State for Defence, what is the estimated cost of the upgrade of submarine docking facilities at Devonport Dockyard; and when that work is due for completion.

Answer

Al Carns
The cost of the current endorsed programme for upgrading submarine docking facilities at Devonport Dockyard is approximately £3 billion. The opening of 9 Dock in September 2024 is the latest of a number of significant investments in Devonport. A range of ...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 5885) →