Written Question·Ministry of Defence·UIN 5885
Devonport Dockyard
Tabled: 4 October 2024
Answered: 15 October 2024
Named DayQuestion
Mr Mark Francois
Conservative — Rayleigh and Wickford
To ask the Secretary of State for Defence, what is the estimated cost of the upgrade of submarine docking facilities at Devonport Dockyard; and when that work is due for completion.
Answer
Al CarnsThe cost of the current endorsed programme for upgrading submarine docking facilities at Devonport Dockyard is approximately £3 billion. The opening of 9 Dock in September 2024 is the latest of a number of significant investments in Devonport. A range of ...
ⓘ