Written Question·Ministry of Defence·UIN 70229

Devonport Dockyard: Infrastructure

Tabled: 22 July 2025
Answered: 1 September 2025

Question

Martin Wrigley

Liberal DemocratNewton Abbot

To ask the Secretary of State for Defence, what estimate his Department has made of the cost of infrastructure improvement works at HMNB Devonport; and whether those works involve the (a) removal, (b) containment and (c) replacement of equipment identifie

Answer

Maria Eagle
The current estimate for the costs of infrastructure improvement works at Devonport including the Naval Base and Dockyard are £5 billion. This important activity, which includes works at HMNB Devonport and investment in Devonport Dockyard, will support th...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 70229) →