To ask the Secretary of State for Defence, what his planned timeline is for the completion of the Devonport Infrastructure Programme.
Answer
Luke PollardThe Defence Investment Plan commits £7.1 billion of infrastructure investment at HMNB Devonport over the next decade as part of Project Royal Oak. This investment will deliver major upgrades and renewal across the Naval Base and Dockyard site. Including e...
ⓘ