Written Question·Department for Energy Security and Net Zero·UIN 71106

Electricity Generation

Tabled: 29 August 2025
Answered: 8 September 2025

Question

Wendy Chamberlain

Liberal DemocratNorth East Fife

To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of waiting times in distribution connections reform.

Answer

Michael Shanks
Distribution-level projects can face significant connection delays, particularly if they could impact on the transmission network. The reformed transmission connections process, currently being implemented, should accelerate connections for many viable di...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 71106) →