Written Question·Home Office·UIN 44836
Emergency Services Network: Finance
Tabled: 7 April 2025
Answered: 28 April 2025
Question
Seamus Logan
Scottish National Party — Aberdeenshire North and Moray East
To ask the Secretary of State for the Home Department, what her Department's original budget for the Emergency Services Network programme was; how much her Department has spent since that programme started; and what the estimated final cost is in (a) real
Answer
Dame Diana JohnsonIn July 2021 the Emergency Services Network (ESN) Full Business case was approved by HM Treasury with a whole life cost of £11.3bn through to 2036/37.In October 2024, HM Treasury approved an updated version of the business case which reflected a change in...
ⓘ