F-35 Aircraft: Procurement

Tabled: 3 June 2025
Answered: 9 June 2025

Question

Ben Obese-Jecty

Conservative — Huntingdon

To ask the Secretary of State for Defence, on what date each batch of the Royal Air Force’s F-35B Lightning II aircraft were (a) ordered, (b) delivered and (c) scheduled to be delivered.

Answer

Maria Eagle
The F-35 programme procures aircraft through annual contracts. The first UK F-35B order was placed in 2009 and delivered in 2012. Between 2009 and 2025, the Ministry of Defence has ordered 48 F-35B aircraft, 38 of which have now been delivered. We are una...
ⓘ