Written Question·Ministry of Defence·UIN 91203

F-35 Aircraft: Procurement

Tabled: 14 November 2025
Answered: 20 November 2025
Named Day

Question

Mr Andrew Snowden

Conservative — Fylde

To ask the Secretary of State for Defence, with reference to paragraph 22 of the report entitled The UK’s F-35 capability, HC 989, published by the National Audit Office on 11 July 2025, if he will set out the updated estimate of the whole‑life cost of the (a) equipment, (b) personnel, (c) infrastructure, (d) fuel, (e) ammunition and (f) total cost of the F‑35 programme.

Answer

Luke Pollard

The F-35 programme reports costs to the Departments and National Infrastructure and Service Transformation Authority (NISTA) policy as a Government Major Projects Portfolio (GMPP). My Department will address the Public Accounts Committee recommendations in the formal Government response to the Committee in due course.