Written Question·Department for Environment, Food and Rural Affairs·UIN 52957
Flood Control: Licensing
Tabled: 16 May 2025
Answered: 22 May 2025
Question
Jonathan Davies
Labour — Mid Derbyshire
To ask the Secretary of State for Environment, Food and Rural Affairs, what the average length of time was between the Environment Agency receiving a flood risk activity permit application and starting the determination process for the approval of said pe
Answer
Emma HardyFlood risk activity permit applications are currently being allocated for assessment a maximum of 14 weeks from receipt. For time critical applications that pose a significant risk to people or the environment, or where required for national infrastructur...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 52957) →