Written Question·Department for Transport·UIN 48694
Great British Railways
Tabled: 28 April 2025
Answered: 8 May 2025
Question
Charlie Dewhirst
Conservative — Bridlington and The Wolds
To ask the Secretary of State for Transport, how much funding has been (a) allocated to and (b) spent by the Great British Railways Transition Team since it was established; and how many external consultants were employed by that team on 28 April 2025.
Answer
Simon LightwoodThe Great British Railways Transition Team (GBRTT) was set up as a temporary organisation under the previous government to design and transition towards Great British Railways, including building cross-industry capability. Total funding allocated to GBRTT...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 48694) →