Question

Charlie Dewhirst

Conservative — Bridlington and The Wolds

To ask the Secretary of State for Transport, how much funding has been (a) allocated to and (b) spent by the Great British Railways Transition Team since it was established; and how many external consultants were employed by that team on 28 April 2025.

Answer

Simon Lightwood
The Great British Railways Transition Team (GBRTT) was set up as a temporary organisation under the previous government to design and transition towards Great British Railways, including building cross-industry capability. Total funding allocated to GBRTT...
ⓘ