Written Question·Ministry of Housing, Communities and Local Government·UIN 81898
High Rise Flats: Construction
Tabled: 14 October 2025
Answered: 22 October 2025
Question
Kevin Hollinrake
Conservative — Thirsk and Malton
To ask the Secretary of State for Housing, Communities and Local Government, on average how many hours are spent reviewing (a) a successful and (b) an unsuccessful application for Gateway 2 approval from the Building Safety Regulator.
Answer
Samantha DixonThe Building Safety Regulator’s (BSR) handling time for each application is dependent on a range of factors, primarily the quality of the application and the additional information submitted by the applicant. As can be seen in the table below, the average...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 81898) →