Question
Ruth Cadbury
Labour — Brentford and Isleworth
To ask the Secretary of State for Housing, Communities and Local Government, what estimate he has made of the average waiting for the Building Safety Regulator to approve the remediation of residential flats in London.
Answer
Samantha DixonThe monthly Building Control Approval Application dataset January 2026 showed that the average approval timeframe for remediation projects in London was 30 weeks.We recognise that processing times need to improve, and we will be bringing forward a Buildin...
ⓘ