Written Question·Ministry of Housing, Communities and Local Government·UIN 80432

High Rise Flats: Insulation

Tabled: 10 October 2025
Answered: 20 October 2025

Question

Lee Pitcher

LabourDoncaster East and the Isle of Axholme

To ask the Secretary of State for Housing, Communities and Local Government, what steps his Department is taking to ensure that cladding remediation works on high-risk buildings are not subject to avoidable delays in the building control approval process

Answer

Samantha Dixon
The Building Safety Regulator (BSR) has established a dedicated external remediation team who assess all building control approval applications for cladding remediation. The team is already delivering engagement events to improve developers’ understanding...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 80432) →