Question
Lee Pitcher
Labour — Doncaster East and the Isle of Axholme
To ask the Secretary of State for Housing, Communities and Local Government, what steps his Department is taking to ensure that cladding remediation works on high-risk buildings are not subject to avoidable delays in the building control approval process
Answer
Samantha DixonThe Building Safety Regulator (BSR) has established a dedicated external remediation team who assess all building control approval applications for cladding remediation. The team is already delivering engagement events to improve developers’ understanding...
ⓘ