To ask the Secretary of State for Housing, Communities and Local Government, what deadline the Government has set for residential freeholders to complete remediation works on buildings with unsafe cladding; and what steps he will take in cases where such
Answer
Samantha DixonIn the Remediation Acceleration Plan, we set a clear target that, by the end of 2029, every residential building over 11 metres with unsafe cladding will have either completed remediation works or have a firm completion date in place, otherwise the respon...
ⓘ