Written Question·Ministry of Housing, Communities and Local Government·UIN 116846
High Rise Flats: Insulation
Tabled: 2 March 2026
Answered: 10 March 2026
Question
Luke Taylor
Liberal Democrat — Sutton and Cheam
To ask the Secretary of State for Housing, Communities and Local Government, what the current average time is between submission and approval of Gateway 2 applications for cladding remediation works on high-risk buildings.
Answer
Samantha DixonThe Building Safety Regulator (BSR) has increased their regulatory capacity throughout 2025. There were 115 posts approved, with 83 members of staff already onboarded. The BSR’s monthly Building Control Approval data was released on 25th February 2026 for...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 116846) →