Written Question·Department for Transport·UIN 194791
High Speed 2 Line
Tabled: 18 July 2023
Answered: 11 September 2023
Named DayQuestion
Mr Tanmanjeet Singh Dhesi
Labour — Slough
To ask the Secretary of State for Transport, what the (a) projected end date is, (b) forecast spend in the financial year 2023-24 is, (c) initial planned whole life costs were and (d) delivery confidence assessment is of HS2 Phase 2b; and when each of tho
Answer
The Government set out schedule and cost updates for the HS2 Phase 2b Western Leg in its 6-monthly report on HS2 to Parliament in June. HS2 services between Crewe and Manchester are expected to begin between 2035 and 2041. The current cost estimate range ...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 194791) →