Written Question·Department for Transport·UIN 44833

High Speed 2 Line

Tabled: 7 April 2025
Answered: 28 April 2025

Question

Seamus Logan

Scottish National PartyAberdeenshire North and Moray East

To ask the Secretary of State for Transport, what her Department's original budget for HS2 Phase 2 was; how much her Department has spent since that project started; and what the estimated final cost is in (a) real and (b) current terms.

Answer

Lilian Greenwood
The original funding envelopes (in 2015 prices) for Phase 2a was £3.72bn and £24.8bn for Phase 2b. Spend on the HS2 project can be found in the latest Parliamentary Report here , which is updated and published at regular intervals. The project currently r...