Written Question·Department for Transport·UIN 93845

High Speed 2 Line

Tabled: 24 November 2025
Answered: 2 December 2025

Question

Jim McMahon

Labour (Co-op)Oldham West, Chadderton and Royton

To ask the Secretary of State for Transport, what (a) land and (b) property acquired for the construction of the HS2 Phase 2 route from Birmingham to Crewe is (1) still held, (2) sale pending and (3) sold.

Answer

Simon Lightwood
337 properties have been acquired for HS2 on the former Phase 2a route between Birmingham and Crewe. These are 122 agricultural units; including land where there are no dwellings, 4 commercial properties and 211 residential properties. No land or property...