High Speed 2 Line: Staffordshire

Tabled: 4 November 2025
Answered: 11 November 2025
Named Day

Question

Mr Richard Holden

Conservative — Basildon and Billericay

To ask the Secretary of State for Transport, pursuant to the Answer of 27 October 2025 to Question 84309 on High Speed 2, what her Department’s latest estimate is of (a) the additional cost arising from the four-year deferral of works between Delta Juncti

Answer

Simon Lightwood
The previous Government paused works between Delta Junction and Handsacre Junction in March 2023. HS2 Ltd provided an estimate at the time in 2023 that the cost of demobilisation of these works was c.£35m (2019 prices). Further deferral will not incur dem...
ⓘ