High Speed 2 Line: Staffordshire

Tabled: 25 March 2026
Answered: 1 April 2026

Question

To ask His Majesty's Government when they will publish impact assessments for the HS2 construction works between Curdworth in Warwickshire and Handsacre in Staffordshire due to commence in March 2027.

Answer

Going back to March 2023, the previous Government asked HS2 Ltd to pause some of the works on the section north of Birmingham. In 2025, this Government agreed to pause the works on the section between Curdworth and Handsacre for a further four years until...
ⓘ