Question
To ask His Majesty's Government what the names of the six major rail tunnel and road milestones completed ahead of schedule in 2025 are, as cited by Rt Hon Darren Jones MP in their announcement on 27 January of the start of boring work on the tunnels betw
Answer
The six major rail tunnel and road milestones completed ahead of schedule in 2025 are as follows: MilestonePlanned DateActual DateA46 – completion of structure – road re-openedMay-25Apr-25Bromford tunnel – tunnel boring machine (TBM) 2 (Elizabeth) breakth...
ⓘ