Written Question·Department for Energy Security and Net Zero·UIN 7946

Hinkley Point C Power Station and Sizewell C Power Station: Compensation

Tabled: 8 October 2024
Answered: 16 October 2024

Question

Carla Denyer

Green PartyBristol Central

To ask the Secretary of State for Energy Security and Net Zero, with reference to the first bullet point on page 23 of EDF Energy Holdings Limited Annual Report and Financial Statements 31 December 2023, what estimate he has made of the amount of compensa

Answer

Michael Shanks
Under the terms of a contractual agreement between HPC and SZC, which was agreed at the time of the Final Investment Decision on HPC, a payment is payable from SZC to HPC if SZC takes a positive FID. This payment reflects benefits for SZC, including the s...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 7946) →