Written Question·Department for Energy Security and Net Zero·UIN 52898
Hinkley Point C Power Station: China General Nuclear Power Corporation
Tabled: 16 May 2025
Answered: 27 May 2025
Question
Mr Richard Holden
Conservative — Basildon and Billericay
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the potential impact of China General Nuclear Power Corporation’s involvement in the construction of Hinkley Point C on cyber-security.
Answer
Michael ShanksTo build and operate a nuclear site, a security plan, which includes cyber security, must be put in place and approved by the Office for Nuclear Regulation (ONR). The ONR, an independent regulator, then ensures that plan is effectively enforced. The secur...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 52898) →