Written Question·Ministry of Justice·UIN 122055

HMP Erlestoke: Construction

Tabled: 18 March 2026
Answered: 24 March 2026
Named Day

Question

Ben Obese-Jecty

Conservative — Huntingdon

To ask the Secretary of State for Justice, pursuant to the Answer of 19 November 2025 to Question 89778 on Prisons: Construction, on what date did ISG Construction Limited cease on-site work at HMP Erlestoke.

Answer

Jake Richards
ISG Construction Limited ceased work on all Ministry of Justice sites on the date of their administration, 20 September 2024. This included the expansion at HMP Erlestoke.Although the sites at HMP Leyhill, HMP Ford and HMP Standford Hill were due to be co...
ⓘ

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 122055) →