Written Question·Department of Health and Social Care·UIN 25253
Hospitals: Construction
Tabled: 21 January 2025
Answered: 27 January 2025
Named DayQuestion
Edward Argar
Conservative — Melton and Syston
To ask the Secretary of State for Health and Social Care, with refence to his oral statement of 20 January 2025 on New Hospital Programme Review, Official Report columns 748-750s, what the (a) pre-construction works, (b) full construction start and (c) co
Answer
Karin SmythThe following table shows the start dates for the pre-construction work, which involves business case development and critical enabling works, and the main construction work, for the schemes requested:SchemePre-construction works startMain construction wo...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 25253) →