Written Question·Department for Environment, Food and Rural Affairs·UIN 117628
Import Controls: Northern Ireland
Tabled: 3 March 2026
Answered: 10 March 2026
Named DayQuestion
Jim Allister
Traditional Unionist Voice — North Antrim
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer of 22 October 2025 to Question 82237 on Import Controls, whether the construction of the border control posts at (i) Belfast, (ii) Larne, (iii) Foyle and (iv) Wa
Answer
Dame Angela EagleIn line with the commitments the Government has made under the Windsor Framework, construction of SPS Inspection Facilities at Belfast, Larne, Foyle, and Warrenpoint are in place and these facilities are operational. Remaining works at the 2 March were li...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 117628) →