Written Question·Ministry of Housing, Communities and Local Government·UIN 57583
Incinerators: Construction
Tabled: 4 June 2025
Answered: 17 June 2025
Question
Lee Barron
Labour — Corby and East Northamptonshire
To ask the Secretary of State for Housing, Communities and Local Government, if her Department will issue guidance on a reasonable timeframe for the (a) construction and (b) completion of an energy recovery facility with a capacity of 350,000 tonnes per y
Answer
Matthew PennycookAll full planning permissions for development, including waste to energy development, are required to be commenced within three years of the grant of permission (unless the local planning authority sets a different time period.) Further guidance on this c...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 57583) →