To ask the Secretary of State for Transport, pursuant to the Answer of 02 December to Question 15995, on Kings Norton Station, whether that £123m to design the first phase of the Midlands Rail Hub programme included any capital funding for (a) the reinsta
Answer
Simon LightwoodThe funding for Midlands Rail Hub includes designs for the reinstatement of the island platforms at Kings Norton, which, subject to a future ‘Decision to Deliver’, could be constructed by the early 2030s. Camp Hill line trains will serve Kings Norton from...
ⓘ